Keeping user changes in a new measurement

Sometimes it is necessary to do a new measurement after some user operations have already been done to define the services. For example: a code change was introduced that may affect the services which requires doing a new measurement, however, if the user wants to maintain the changes like the service endpoints and other configurations then the new measurement should use an existing measurement (with the user changes) as baseline.

Procedure:

  1. Go to Learning and do New Measurement (close the installation guide if it shows up)
  2. Click SET BASELINE at the bottom and select the measurement where the changes you want to maintain exist
  3. Click Start to start the new data collection